1512 S POINT VIEW ST 90035

Certificate Information: 1512 S POINT VIEW ST 90035

Application / Permit
21016-30000-09324
Plan Check / Job No.
B21WL01592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU WITH ADDTION
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 TARIK SAOUD
Corrections Issued 4/21/2021 TARIK SAOUD
Quality Review Completed 4/29/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/20/2021 TARIK SAOUD
Issued 9/14/2021 APPLICANT
CofO in Progress 9/18/2023 JOSE AVILA
Permit Finaled 9/21/2023 DEROLD HAUFF
CofO Issued 9/21/2023 DEROLD HAUFF
Permit Finaled 9/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/13/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 5/13/2021 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 5/20/2021 CELINA MORENO
Sewer availability Cleared 5/20/2021 CELINA MORENO
Hydrant and Access approval Cleared 7/7/2021 GREGORY HOERNER
Low Impact Development Cleared 7/29/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/3/2021 THOMAS LANG
Construction near power lines Cleared 8/10/2021 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2021 Approved JOSE AVILA
Footing/Foundation/Slab 12/13/2021 Approved JOSE AVILA
METHANE-Barrier 12/13/2021 Approved JOSE AVILA
METHANE-Subgrade 12/13/2021 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Approved JOSE AVILA
PLUMBING-Rough 3/17/2022 Not Ready for Inspection JOSE AVILA
Sewer 3/17/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 3/24/2022 Approved JOSE AVILA
Sewer 3/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/7/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/7/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Approved JOSE AVILA
Green Building Rough 11/7/2022 Corrections Issued JOSE AVILA
HVAC-Rough 11/7/2022 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 11/7/2022 Not Ready for Inspection JOSE AVILA
METHANE-Rough 11/7/2022 Approved JOSE AVILA
PLUMBING-Rough 11/7/2022 Approved JOSE AVILA
Insulation 11/17/2022 Approved JOSE AVILA
Drywall Nailing 11/28/2022 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 No Access for Inspection JOSE AVILA
BUILDING-Rough-Frame 1/3/2023 Partial Approval JOSE AVILA
Drywall Nailing 1/3/2023 Approved JOSE AVILA
Service/Power Release 3/28/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 6/20/2023 Approved JOSE AVILA
Final 6/20/2023 Corrections Issued JOSE AVILA
Green Building Rough 6/20/2023 Approved JOSE AVILA
Final 7/19/2023 Corrections Issued JOSE AVILA
Green Building Final 7/19/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 7/19/2023 Approved JOSE AVILA
Final 9/18/2023 OK to Issue CofO JOSE AVILA