875 S COMSTOCK AVE #10B 90024
Certificate Information: 875 S COMSTOCK AVE #10B 90024
- Application / Permit
- 21016-30000-09108
- Plan Check / Job No.
- B21WL01568
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- REMODEL BATHROOM, REMOVE AND REPLACE NON-BEARING PARTIOTION WALL.
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- Issued on 5/26/2021
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | KHUONG TRUONG |
| Corrections Issued | 4/13/2021 | KHUONG TRUONG |
| Plan Check Approved | 5/17/2021 | KHUONG TRUONG |
| Issued | 5/26/2021 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/26/2021 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 4/26/2021 | DENZEL HENDERSON |
| ZI | Cleared | 4/29/2021 | JOE LUCKEY |
Contact Information
| Contractor | J L S Development Inc; Lic. No.: 919951-B | 24007 VENTURA BLVD #207 CALABASAS, CA 91302 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/2/2021 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 6/8/2021 | Approved | PAUL DAVIDSON |
| Insulation | 6/8/2021 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 6/8/2021 | Approved | PAUL DAVIDSON |
| Final | 9/20/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 9/20/2021 | Approved | PAUL DAVIDSON |
| METHANE-Final | 9/20/2021 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 9/20/2021 | Approved | PAUL DAVIDSON |
| Smoke Detectors | 9/20/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 9/23/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Smoke Detectors | 9/23/2021 | Approved | PAUL DAVIDSON |