4223 W RUSSELL AVE 90027
Certificate Information: 4223 W RUSSELL AVE 90027
- Application / Permit
- 21016-30000-08493
- Plan Check / Job No.
- B21WL01472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF EXISTING FIRST FLOOR TO EXPAND EXISTING BATHROOM IN (E) SFD
- Permit Issued
- Issued on 7/30/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | JASON JANGADA |
| Corrections Issued | 4/23/2021 | JASON JANGADA |
| Applicant returned to address corrections | 6/3/2021 | HOOMAN HAJIZADEH |
| Plan Check Approved | 6/3/2021 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 7/8/2021 | APPLICANT |
| Issued | 7/30/2021 | APPLICANT |
| CofO in Progress | 2/9/2022 | JOSEPH MCGARRY |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/3/2021 | JASON JANGADA |
Contact Information
| Contractor | F M Mercado Construction Inc; Lic. No.: 991282-B | 1112 E 22ND STREET LOS ANGELES, CA 90011 |
| Engineer | Shun,, Hai-Ray; Lic. No.: C42961 | 9817 MILOANN STREET TEMPLE CITY, CA 91780 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 9/29/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/29/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/18/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/18/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/18/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/18/2021 | Approved | JOSEPH MCGARRY |
| Sewer | 10/18/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 10/20/2021 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 10/22/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/22/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/27/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/27/2021 | Approved | JOSEPH MCGARRY |
| Final | 1/14/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 1/14/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/9/2022 | Approved | JOSEPH MCGARRY |
| Final | 2/9/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 2/9/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/9/2022 | Approved | JOSEPH MCGARRY |