3967 S BEETHOVEN ST 90066

Certificate Information: 3967 S BEETHOVEN ST 90066

Application / Permit
21016-30000-08483
Plan Check / Job No.
B21WL01466
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage (367 SF) to accessory dwelling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 11/17/2021
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/9/2021 RICHARD GARCIA
Corrections Issued 4/10/2021 RICHARD GARCIA
Applicant returned to address corrections 7/15/2021 JASON JANGADA
Plan Check Approved 9/2/2021 JASON JANGADA
Issued 11/17/2021 APPLICANT
CofO in Progress 1/9/2023 JESUS RODRIGUEZ
Permit Finaled 1/19/2023 DANIEL ORRANTE
CofO Issued 1/19/2023 DANIEL ORRANTE
Permit Finaled 1/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/29/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 4/29/2021 DINAH GARIN
Sewer availability Cleared 4/29/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/4/2021 DINAH GARIN
Specific Plan Cleared 5/18/2021 LOUIS ORTEGA
ZI Cleared 5/18/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 6/25/2021 KURT CORRAL

Contact Information

Contractor M R D Construction; Lic. No.: 960463-B 13719 VENTURA BLVD UNIT D      SHERMAN OAKS, CA 91423
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/8/2022 Corrections Issued DAVID FEILER
Sewer 2/8/2022 Not Ready for Inspection DAVID FEILER
Underground Mechanical 2/8/2022 Not Ready for Inspection DAVID FEILER
Deputy Reinf. Concrete 2/15/2022 Approved ENRIQUE MIRELES
Underground Mechanical 2/15/2022 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 2/16/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/16/2022 Approved ENRIQUE MIRELES
Underground Mechanical 2/16/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/5/2022 Corrections Issued PATRICK QUALEY
Green Building Rough 5/5/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 5/5/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 6/3/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/3/2022 Corrections Issued STEPHANIE SWANSON
Wood Frame 6/3/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/17/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 6/17/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 6/17/2022 Approved STEPHANIE SWANSON
Insulation 6/28/2022 Corrections Issued PATRICK QUALEY
Wood Frame 6/28/2022 Partial Inspection PATRICK QUALEY
Insulation 7/7/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Not Ready for Inspection PATRICK QUALEY
Shower Pan 7/22/2022 Corrections Issued PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 7/29/2022 Approved DAVID FEILER
Shower Pan 7/29/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 8/4/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved JESUS RODRIGUEZ
Green Building Rough 8/4/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 8/16/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/29/2022 Approved JESUS RODRIGUEZ
Final 11/29/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/29/2022 Approved JESUS RODRIGUEZ
HVAC-Final 11/29/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/29/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/29/2022 Approved JESUS RODRIGUEZ
Final 1/9/2023 OK to Issue CofO JESUS RODRIGUEZ