525 N LAUREL AVE 90048
Certificate Information: 525 N LAUREL AVE 90048
- Application / Permit
- 21016-30000-08250
- Plan Check / Job No.
- B21WL01401
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel thoughout an existing 1-story SFD. Relocte family room, kitchen, dining room, bedrooms & bathrooms, add guest bedroom & bathroom, laundry room, 1/2 bath and replaceme exterior doors and windows.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/3/2025
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/8/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 4/20/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 5/12/2021 | JAHANSHAH POURHASSAN |
| Issued | 6/7/2021 | APPLICANT |
| Permit Finaled | 6/2/2025 | JOSE MACIAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Rees,, Robert S; Lic. No.: C26934 | 3483 BARRY AVENUE LOS ANGELES, CA 90066 |
| Contractor | D & J Optimum Development; Lic. No.: 1037421-B | 17844 HARTLAND ST RESEDA, CA 91335 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/3/2021 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 9/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/5/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/29/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/2/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 3/7/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/22/2022 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 3/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | ADAM ESCOTO |
| Final | 5/23/2025 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 5/23/2025 | Approved | JOSE MACIAS |
| Final | 6/2/2025 | Permit Finaled | JOSE MACIAS |