9366 W AIRDROME ST 90035
Certificate Information: 9366 W AIRDROME ST 90035
- Application / Permit
- 21016-30000-07809
- Plan Check / Job No.
- B21WL01334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2023
Permit Application Status History
| Submitted | 3/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | ALFREDO JARA |
| Corrections Issued | 3/31/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 4/23/2021 | KHUONG TRUONG |
| Plan Check Approved | 5/7/2021 | ALFREDO JARA |
| Issued | 1/12/2022 | APPLICANT |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Permit Finaled | 1/25/2023 | ASHLEY THOMPSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/7/2021 | ALFREDO JARA |
Contact Information
| Contractor | Arrow Construction & Remodeling Inc; Lic. No.: 718685-B | 1749 SOUTH SHERBOURNE DRIVE LOS ANGELES, CA 90035 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/16/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 5/16/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/25/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/2/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/2/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/2/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 6/6/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/9/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 6/13/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/24/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 6/24/2022 | Approved | KEVIN SARGSYAN |
| Final | 1/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 1/13/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 1/13/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/25/2023 | Approved | ASHLEY THOMPSON |
| Final | 1/25/2023 | Permit Finaled | ASHLEY THOMPSON |
| HVAC-Final | 1/25/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/25/2023 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 1/25/2023 | Approved | ASHLEY THOMPSON |