730 N CHEROKEE AVE 90038
Certificate Information: 730 N CHEROKEE AVE 90038
- Application / Permit
- 21016-30000-07104
- Plan Check / Job No.
- B21WL01241
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached 2-car garage into ADU and attached patio.PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | RICHARD GARCIA |
| Corrections Issued | 4/3/2021 | RICHARD GARCIA |
| Plan Check Approved | 9/24/2021 | ALFREDO JARA |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 5/27/2022 | BRIAN SULLIVAN |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
| CofO Issued | 3/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/3/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 8/13/2021 | JOHN CONNEALLY |
| ZI | Cleared | 9/14/2021 | RICHARD REASER |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/29/2021 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 10/29/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/29/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/6/2021 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 12/6/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 12/6/2021 | Corrections Issued | BRIAN SULLIVAN |
| METHANE-Rough | 12/6/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/6/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 12/6/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 3/10/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/15/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 3/15/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/15/2022 | Approved | BRIAN SULLIVAN |
| Shower Pan | 3/15/2022 | Approved | BRIAN SULLIVAN |
| Final | 5/16/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/26/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | BRIAN SULLIVAN |