8128 S HOLY CROSS PL 90045
Certificate Information: 8128 S HOLY CROSS PL 90045
- Application / Permit
- 21016-30000-06601
- Plan Check / Job No.
- B21WL01130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) KITCHEN, LIVING RM, DINNING, BEDRM, AND BATH, REMOVE FIREPLACE AND CHIMNEY, REMOVE SKYLIIGHT IN AN (E) SINGLE STORY SFD.
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/14/2022
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 3/16/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 4/13/2021 | DAVID CASTILLO |
| Issued | 6/24/2021 | APPLICANT |
| Permit Finaled | 3/14/2022 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Gelfat,, James Evan; Lic. No.: C19847 | 10748 FLAXTON ST CULVER CITY, CA 90230 |
| Contractor | Circa 65 Construction Inc; Lic. No.: 653492-B | 4818 IMLAY AVE CULVER CITY, CA 90230 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/17/2021 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/3/2021 | Approved | BRENDAN LOONEY |
| Wood Frame | 9/29/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/1/2021 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 10/1/2021 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 10/7/2021 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 11/17/2021 | Approved | BOBBY KEY |
| Wood Frame | 11/19/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/22/2021 | Approved | JOHN KAYON |
| Insulation | 11/23/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 12/1/2021 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/13/2021 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 12/15/2021 | Approved | BOBBY KEY |
| Final | 3/7/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 3/7/2022 | Approved | ANDREW NAVE |
| Final | 3/14/2022 | Permit Finaled | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | BOBBY KEY |