8128 S HOLY CROSS PL 90045

Certificate Information: 8128 S HOLY CROSS PL 90045

Application / Permit
21016-30000-06601
Plan Check / Job No.
B21WL01130
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) KITCHEN, LIVING RM, DINNING, BEDRM, AND BATH, REMOVE FIREPLACE AND CHIMNEY, REMOVE SKYLIIGHT IN AN (E) SINGLE STORY SFD.
Permit Issued
Issued on 6/24/2021
Issuing Office
Current Status
Permit Finaled on 3/14/2022

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/16/2021 JAHANSHAH POURHASSAN
Corrections Issued 3/16/2021 JAHANSHAH POURHASSAN
Plan Check Approved 4/13/2021 DAVID CASTILLO
Issued 6/24/2021 APPLICANT
Permit Finaled 3/14/2022 BOBBY KEY

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Gelfat,, James Evan; Lic. No.: C19847 10748 FLAXTON ST      CULVER CITY, CA 90230
Contractor Circa 65 Construction Inc; Lic. No.: 653492-B 4818 IMLAY AVE      CULVER CITY, CA 90230
Engineer Parker,, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 8/17/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 9/3/2021 Approved BRENDAN LOONEY
Wood Frame 9/29/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 10/1/2021 Partial Approval BRENDAN LOONEY
Wood Frame 10/1/2021 Partial Approval BRENDAN LOONEY
Wood Frame 10/7/2021 Approved BRENDAN LOONEY
Pre-Inspection 11/17/2021 Approved BOBBY KEY
Wood Frame 11/19/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/22/2021 Approved JOHN KAYON
Insulation 11/23/2021 Approved BOBBY KEY
Drywall Nailing 12/1/2021 Approved BOBBY KEY
Interior/Exterior Lathing 12/13/2021 Partial Approval BOBBY KEY
Interior/Exterior Lathing 12/15/2021 Approved BOBBY KEY
Final 3/7/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 3/7/2022 Approved ANDREW NAVE
Final 3/14/2022 Permit Finaled BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved BOBBY KEY