2365 E CENTURY BLVD SUITE D 90002
Certificate Information: 2365 E CENTURY BLVD SUITE D 90002
- Application / Permit
- 21016-30000-06206
- Plan Check / Job No.
- B21WL01070
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RETAIL TO RESTAURANT FOR SUITE # D
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- Issued on 7/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | TARIK SAOUD |
| Corrections Issued | 3/23/2021 | TARIK SAOUD |
| Quality Review Completed | 3/31/2021 | KAMRAN GHOTBI RAVANDI |
| Disabled Access Plans Picked Up | 5/5/2021 | APPLICANT |
| Plan Check Approved | 7/29/2021 | CHIHARU SUZUKI |
| Issued | 7/29/2021 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| ZA Case | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| ZA Case | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| ZA Case | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| ZA Case | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| ZA Case | Cleared | 5/5/2021 | JEANALEE OBERGFELL |
| DAS Clearance | Cleared | 6/29/2021 | TARIK SAOUD |
| Food Service Establishment | Cleared | 6/30/2021 | PAWAN VERMA |
| Food establishment approval | Cleared | 7/28/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Willis Construction Company; Lic. No.: 1020831-B | 15138 ELMBROOK DR LA MIRADA, CA 90638 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/10/2021 | Corrections Issued | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 8/12/2021 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 8/26/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/30/2021 | Approved | DANIEL COLLINS |
| T-Bar Ceiling | 10/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/22/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 11/22/2021 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 11/22/2021 | Approved | RUSSELL BONVOULOIR |