3937 S SUTRO AVE 90008
Certificate Information: 3937 S SUTRO AVE 90008
- Application / Permit
- 21016-30000-05246
- Plan Check / Job No.
- B21WL00900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE TO ADU.PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | ALFREDO JARA |
| Corrections Issued | 3/8/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 4/12/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/20/2021 | ALFREDO JARA |
| Plan Check Approved | 6/23/2021 | ALFREDO JARA |
| Issued | 8/26/2021 | APPLICANT |
| CofO in Progress | 9/21/2022 | ANTHONY EGSON |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 3/22/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/22/2021 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 5/1/2021 | JOHN CONNEALLY |
| Construction within easement | Cleared | 6/4/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Everlasting Construction & Design Inc; Lic. No.: 1003948-B | 5117 HEINTZ STREET #7 BALDWIN PARK, CA 91706 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/3/2021 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 9/9/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/9/2021 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 9/9/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/13/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 9/13/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 10/22/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/22/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 10/22/2021 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/26/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/26/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 10/26/2021 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 11/1/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/9/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/9/2021 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 11/9/2021 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/15/2021 | Approved | ANTHONY EGSON |
| Insulation | 11/18/2021 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/19/2021 | Approved | ANTHONY EGSON |
| Shower Pan | 11/19/2021 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 11/23/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Shower Pan | 11/23/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 11/29/2021 | Approved | ANTHONY EGSON |
| Final | 1/21/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/21/2022 | Approved | ANTHONY EGSON |
| Final | 1/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Inspection | 2/3/2022 | Partial Inspection | ANTHONY EGSON |
| Final | 8/17/2022 | OK to Issue CofO | ANTHONY EGSON |