3110 N HOLLYRIDGE DR 90068
Certificate Information: 3110 N HOLLYRIDGE DR 90068
- Application / Permit
- 21016-30000-04016
- Plan Check / Job No.
- B21WL00670
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) 2-Story Single family dwelling per engineering desgin. No change in (E) footprint.
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/24/2022
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | ALFREDO JARA |
| Corrections Issued | 2/26/2021 | ALFREDO JARA |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| Plan Check Approved | 9/24/2021 | ALFREDO JARA |
| Issued | 10/5/2021 | APPLICANT |
| Permit Finaled | 8/23/2022 | BRIAN SULLIVAN |
Permit Application Clearance Information
| ZA Case | Cleared | 9/2/2021 | RICHARD REASER |
| Specific Plan | Cleared | 9/14/2021 | LIKYELESH ABERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 12/28/2021 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 1/31/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/31/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 1/31/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/4/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/4/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/4/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/4/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 2/15/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/15/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 2/22/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 3/1/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | BRIAN SULLIVAN |
| Final | 8/4/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 8/4/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 8/4/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 8/4/2022 | Approved | BRIAN SULLIVAN |
| Final | 8/23/2022 | Permit Finaled | BRIAN SULLIVAN |