6656-6658 N CAPISTRANO AVE 91307
Certificate Information: 6656-6658 N CAPISTRANO AVE 91307
- Application / Permit
- 21016-30000-03950
- Plan Check / Job No.
- B21WL00656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) Attached garage to ADU.Per WFPP. PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 8/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | ALFREDO JARA |
| Corrections Issued | 4/12/2021 | ALFREDO JARA |
| Plan Check Approved | 6/30/2021 | ALFREDO JARA |
| Issued | 8/29/2021 | APPLICANT |
| CofO in Progress | 1/12/2023 | TROY SANDERS |
| Permit Finaled | 2/27/2023 | JOHN JANSON |
| CofO Issued | 2/27/2023 | JOHN JANSON |
| Permit Finaled | 2/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/15/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 6/21/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/3/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 6/24/2022 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 6/27/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 6/27/2022 | Corrections Issued | TROY SANDERS |
| PLUMBING-Rough | 6/27/2022 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 7/7/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 7/7/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 7/7/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 7/25/2022 | Corrections Issued | DAVID SANDOVAL |
| Drywall Nailing | 8/31/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 8/31/2022 | Not Ready for Inspection | TROY SANDERS |
| Pre-Inspection | 10/6/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Drywall Nailing | 11/1/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | TROY SANDERS |
| Final | 12/7/2022 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/7/2022 | Approved | TROY SANDERS |
| Final | 1/12/2023 | OK to Issue CofO | TROY SANDERS |
| Special/Order Compliance | 2/21/2023 | Approved | TROY SANDERS |