548 N CAHUENGA BLVD 90004
Certificate Information: 548 N CAHUENGA BLVD 90004
- Application / Permit
- 21016-30000-03431
- Plan Check / Job No.
- B21WL00614
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) 1 story detached garage into an ADU per GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | RICHARD GARCIA |
| Corrections Issued | 2/20/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 7/15/2021 | MARJAN SHENASI |
| Plan Check Approved | 2/10/2022 | RICHARD GARCIA |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| CofO in Progress | 8/15/2023 | JEFFREY MEAD |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
| CofO Issued | 8/21/2023 | DEROLD HAUFF |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/3/2021 | ROSA SILVA |
| HPOZ | Cleared | 4/20/2021 | SUKI GERSHENHORN |
| ZI | Cleared | 4/20/2021 | SUKI GERSHENHORN |
| CPC | Cleared | 7/22/2021 | SUKI GERSHENHORN |
| Hydrant and Access approval | Cleared | 10/3/2021 | ROBERT DUFF |
| Construction near power lines | Cleared | 1/20/2022 | TINA MIRANDA |
Contact Information
| Architect | Didvar-Saadi,, Sarah; Lic. No.: C25408 | 4241 TIVOLI AVENUE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 4/5/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 5/4/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 5/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| METHANE-Rough | 5/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Inspection | 5/10/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 6/8/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/8/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/8/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/8/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| METHANE-Rough | 6/8/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/21/2022 | Approved | JEFFREY MEAD |
| Insulation | 7/21/2022 | Approved | JEFFREY MEAD |
| Wood Frame | 7/21/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/19/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/19/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 8/19/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | JOSEPH MCGARRY |
| Final | 12/9/2022 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Final | 12/9/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 12/9/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 12/9/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/20/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Final | 4/4/2023 | Partial Inspection | JEFFREY MEAD |
| Final | 4/4/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 4/4/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 4/4/2023 | Approved | JEFFREY MEAD |
| Final | 4/5/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/15/2023 | OK to Issue CofO | JEFFREY MEAD |