12916 1/2 W VENICE BLVD 90066
Certificate Information: 12916 1/2 W VENICE BLVD 90066
- Application / Permit
- 21016-30000-03286
- Plan Check / Job No.
- B21WL00582
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert (E) Storage Room and Half Bath into an ADU per GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 1/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | RICHARD GARCIA |
| Corrections Issued | 2/21/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/5/2021 | JASON JANGADA |
| Plan Check Approved | 6/10/2021 | DAVID CASTILLO |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 1/13/2022 | ENRIQUE MIRELES |
| CofO in Progress | 1/13/2022 | ENRIQUE MIRELES |
| Permit Finaled | 1/20/2022 | DANIEL ORRANTE |
| CofO Issued | 1/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/12/2021 | DANIEL CORONADO |
| Address approval | Cleared | 3/16/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | DINAH GARIN |
| Specific Plan | Cleared | 4/12/2021 | FREDDY GARCIA |
| Sewer availability | Cleared | 4/21/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/24/2021 | ROBERT DUFF |
Contact Information
| Architect | Gordon,, Brant Douglas; Lic. No.: C24403 | 12806 PACIFIC AVE 8 LOS ANGELES, CA 90066 |
| Contractor | Time To Build Inc A; Lic. No.: 838931-B | 23037 BIRCH GLEN CIRCLE VALENCIA, CA 91354 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/6/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/9/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/9/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/13/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/20/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/20/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 8/26/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/7/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/7/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 9/7/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/10/2021 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 9/24/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/19/2021 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/19/2021 | Approved | ENRIQUE MIRELES |
| Final | 1/13/2022 | OK to Issue CofO | ENRIQUE MIRELES |