1108 S WETHERLY DR 90035

Certificate Information: 1108 S WETHERLY DR 90035

Application / Permit
21016-30000-03283
Plan Check / Job No.
B21WL00580
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Rmodel to (e) 2-story s.f.d. new kitchen, new bathrooms, new bedrooms and new covered open patio under (e) footprint. Per engineering design.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
Permit Finaled on 3/7/2023

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 ALFREDO JARA
Corrections Issued 2/18/2021 ALFREDO JARA
Plan Check Approved 3/12/2021 ALFREDO JARA
Issued 3/15/2021 APPLICANT
Permit Finaled 3/6/2023 JEREMY TODD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/1/2021 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 3/1/2021 CATHERINE ADROVER
Sewer availability Cleared 3/1/2021 CATHERINE ADROVER
Grading Pre-Inspection Cleared 3/4/2021 BRIAN MILLER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Braum Construction And Management; Lic. No.: 959860-B 6551 VAN NUYS BLVD, MEZZ FLOOR      VAN NUYS, CA 91401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 12/17/2021 Approved EVAN COOPER
Interior/Exterior Lathing 3/14/2022 Partial Approval EVAN COOPER
HVAC-Rough 3/31/2022 Corrections Issued EVAN COOPER
HVAC-Rough 4/5/2022 Conditional Approval EVAN COOPER
PLUMBING-Rough 4/8/2022 Approved EVAN COOPER
ELECTRICAL-Rough 4/28/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/3/2022 Partial Approval EVAN COOPER
Wood Frame 5/3/2022 Corrections Issued EVAN COOPER
Insulation 5/10/2022 Approved EVAN COOPER
Drywall Nailing 5/24/2022 Approved EVAN COOPER
Shower Pan 5/24/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/14/2022 Approved EVAN COOPER
HVAC-Final 12/1/2022 Corrections Issued EVAN COOPER
PLUMBING-Final 12/1/2022 Corrections Issued EVAN COOPER
Service/Power Release 12/1/2022 Approved EVAN COOPER
ELECTRICAL-Final 12/8/2022 Partial Approval CLAYTON GRAHAM
Gas Test 12/8/2022 Approved CLAYTON GRAHAM
PLUMBING-Final 12/8/2022 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 12/13/2022 Not Ready for Inspection JEREMY TODD
Final 12/13/2022 Not Ready for Inspection JEREMY TODD
HVAC-Final 12/13/2022 Not Ready for Inspection JEREMY TODD
PLUMBING-Final 12/13/2022 Not Ready for Inspection JEREMY TODD
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved JEREMY TODD
Smoke Detectors 12/13/2022 Not Ready for Inspection JEREMY TODD
Service/Power Release 1/9/2023 Approved MICHAEL PELHAM
ELECTRICAL-Final 1/11/2023 Corrections Issued JEREMY TODD
Smoke Detectors 1/11/2023 Approved JEREMY TODD
ELECTRICAL-Final 2/27/2023 Partial Approval JEREMY TODD
Final 2/27/2023 Not Ready for Inspection JEREMY TODD
HVAC-Final 2/27/2023 Corrections Issued JEREMY TODD
PLUMBING-Final 2/27/2023 Corrections Issued JEREMY TODD
Final 3/6/2023 Permit Finaled JEREMY TODD