12022 N WIMBERLY AVE 91342

Certificate Information: 12022 N WIMBERLY AVE 91342

Application / Permit
21016-30000-03269
Plan Check / Job No.
B21WL00576
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20'-2" X 20'-2" DETACHED GARAGE INTO ADU PER GOVT.CODE 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 KAVIAN REFAHI
Corrections Issued 2/20/2021 KAVIAN REFAHI
Issued 9/1/2021 APPLICANT
Building Plans Picked Up 9/2/2021 APPLICANT
CofO in Progress 10/28/2022 JENNIFER RABUCHIN
Permit Finaled 10/29/2022 MICHAEL SMITH
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/1/2021 PATRICK MISCHLICH
Address approval Cleared 5/12/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/12/2021 ADRIAN CASTRO
Sewer availability Cleared 5/12/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/24/2021 KURT CORRAL
Construction near power lines Cleared 8/6/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 3/31/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/23/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/23/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/3/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/3/2022 Approved JENNIFER RABUCHIN
Sewer 6/3/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 6/3/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/10/2022 Approved JENNIFER RABUCHIN
Insulation 6/10/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/10/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 7/8/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/18/2022 Approved JENNIFER RABUCHIN
Final 10/18/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/18/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/21/2022 Approved JENNIFER RABUCHIN
Final 10/21/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/21/2022 Approved JENNIFER RABUCHIN
HVAC-Final 10/21/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/21/2022 Approved JENNIFER RABUCHIN