1125-1125 3/4 N LODI PL 90038

Certificate Information: 1125-1125 3/4 N LODI PL 90038

Application / Permit
21016-30000-03263
Plan Check / Job No.
B21WL00575
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
convert an existing 2 car garage to 372 sf one bedroom ADU per CA Govt. Code 65852.2(e)(1)(C). **SEE COMMENTS**
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 KAVIAN REFAHI
Corrections Issued 2/20/2021 KAVIAN REFAHI
Applicant returned to address corrections 3/16/2021 MARJAN SHENASI
Applicant returned to address corrections 3/25/2021 ALFREDO JARA
Plan Check Approved 4/2/2021 KAVIAN REFAHI
Issued 4/19/2021 APPLICANT
CofO in Progress 10/13/2023 JOAQUIN GREENOUGH
No Progress 10/19/2023 SCOTT FINNILA
CofO in Progress 11/22/2023 JOAQUIN GREENOUGH
CofO in Progress 11/22/2023 JOAQUIN GREENOUGH
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/3/2021 ISMAEL HERNANDEZ
ZA Case Cleared 3/4/2021 KENTON TRINH
Address approval Cleared 3/5/2021 JEANIE LAM
Sewer availability Cleared 3/5/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/8/2021 JEANIE LAM

Contact Information

Contractor Largo Construction Inc; Lic. No.: 1011935-B 5864 EAST RANCHO DRIVE      FRESNO, CA 93727
Engineer Khanlou,, Amir; Lic. No.: C87550 10671 HOLMAN AVE   APT 207    LOS ANGELES, CA 90024

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Footing/Foundation/Slab 1/24/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 2/18/2022 Approved STUART CHAPMAN
Sewer 2/18/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 2/23/2022 No Access for Inspection BRIAN SULLIVAN
Deputy Wood Construction 6/9/2022 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/15/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 6/15/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 6/16/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Rough 6/21/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 6/21/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 6/22/2022 Corrections Issued STUART CHAPMAN
HVAC-Rough 6/22/2022 Approved STUART CHAPMAN
PLUMBING-Rough 6/30/2022 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 7/9/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/28/2022 Conditional Approval JOAQUIN GREENOUGH
Wood Frame 12/15/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/19/2023 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/23/2023 Corrections Issued BRIAN SULLIVAN
Drywall Nailing 1/23/2023 Partial Approval BRIAN SULLIVAN
Deputy Wood Construction 1/27/2023 Conditional Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 2/13/2023 Approved BRIAN SULLIVAN
Drywall Nailing 2/28/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 2/28/2023 Approved JOAQUIN GREENOUGH
HVAC-Final 8/14/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 8/14/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 8/21/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 9/28/2023 Approved JOAQUIN GREENOUGH
Final 9/28/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 9/28/2023 Approved JOAQUIN GREENOUGH
Final 10/3/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved JOAQUIN GREENOUGH
Final 10/11/2023 Conditional Approval JOAQUIN GREENOUGH
Final 10/13/2023 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 10/13/2023 Approved JOAQUIN GREENOUGH
Special/Order Compliance 10/17/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 10/21/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 10/25/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 11/20/2023 Corrections Issued JOAQUIN GREENOUGH
Final 11/22/2023 OK to Issue CofO JOAQUIN GREENOUGH