3640 E WHITTIER BLVD 90023
Certificate Information: 3640 E WHITTIER BLVD 90023
- Application / Permit
- 21016-30000-02409
- Plan Check / Job No.
- B21WL00448
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Fire damage repair to (e) roof rafters, interior remodel to (e) chapel and admin office
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/19/2024
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | REZA HAGHIGHAT |
| Corrections Issued | 2/17/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 2/22/2021 | TARIK SAOUD |
| Disabled Access Plans Picked Up | 2/23/2021 | APPLICANT |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| Plan Check Approved | 10/20/2021 | REZA HAGHIGHAT |
| Issued | 11/9/2021 | APPLICANT |
| Permit Finaled | 12/13/2023 | RICARDO ROBLES |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 3/16/2021 | DAVID URITA |
| ZI | Cleared | 3/16/2021 | DAVID URITA |
| DAS Clearance | Cleared | 8/5/2021 | SHINE LIN |
| ZI | Cleared | 8/10/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/22/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2022 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/1/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 8/31/2022 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 8/31/2022 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 9/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 9/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/7/2022 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/21/2022 | Approved | KATY RAMIREZ |
| Pre-Inspection | 11/3/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 11/23/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 12/13/2022 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 2/6/2023 | Not Ready for Inspection | JAIME RIOS |
| Wood Frame | 2/8/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Drywall Nailing | 5/22/2023 | Approved | JULIAN CAPUCETTI |
| Final | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 12/13/2023 | Permit Finaled | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 12/13/2023 | Approved | RICARDO ROBLES |