256 S WOODRUFF AVE 90024
Certificate Information: 256 S WOODRUFF AVE 90024
- Application / Permit
- 21016-30000-01718
- Plan Check / Job No.
- B21WL00096
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Garage to ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | DAVID CASTILLO |
| Corrections Issued | 1/29/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/4/2021 | TARIK SAOUD |
| Plan Check Approved | 2/10/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 10/2/2024 | STEPHANIE SWANSON |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
| CofO Issued | 10/8/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/27/2021 | TRACY TATE |
| Sewer availability | Cleared | 5/27/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | TRACY TATE |
| Address approval | Cleared | 6/7/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 2/8/2022 | DAVID CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | De, Guzman, Nicolo Klaus Dumlao; Lic. No.: C76675 | 9506 ARBORGLEN DRIVE RANCHO CUCAMONGA, CA 91730 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2022 | Conditional Approval | MICHAEL PELHAM |
| Final | 8/4/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/4/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/4/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/27/2023 | Approved | STEPHANIE SWANSON |
| Sewer | 6/27/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/7/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 7/7/2023 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 8/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 8/15/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/15/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/21/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/8/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 12/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 12/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 12/8/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 12/8/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/13/2023 | Approved | STEPHANIE SWANSON |
| Final | 12/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 12/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 12/13/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/22/2024 | Approved | STEPHANIE SWANSON |
| Final | 10/2/2024 | OK to Issue CofO | STEPHANIE SWANSON |