6326 W 82ND ST 90045

Certificate Information: 6326 W 82ND ST 90045

Application / Permit
21016-30000-01637
Plan Check / Job No.
B21WL00302
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Structural remodel of the existing kitchen, laundry, & bath. Re-frame roof area. Replacement of 2 exterior doors and 3 windows.
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
Permit Finaled on 2/10/2023

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 RICHARD GARCIA
Corrections Issued 2/1/2021 RICHARD GARCIA
Plan Check Approved 3/2/2021 RICHARD GARCIA
Building Plans Picked Up 3/4/2021 APPLICANT
Issued 7/27/2021 APPLICANT
Permit Finaled 2/9/2023 HERBERT GIRON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Leigh Construction; Lic. No.: 782532-B 6511 81ST      LOS ANGELES, CA 90045
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/5/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 9/2/2021 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 2/17/2022 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 2/17/2022 Partial Approval DAVID FEILER
HVAC-Rough 2/17/2022 Approved DAVID FEILER
PLUMBING-Rough 2/17/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 2/23/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 2/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 2/23/2022 Approved JESUS RODRIGUEZ
Insulation 3/23/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 4/4/2022 Approved RICHARD STEINBACH
Interior/Exterior Lathing 4/4/2022 Partial Approval RICHARD STEINBACH
Interior/Exterior Lathing 4/18/2022 Approved JESUS RODRIGUEZ
Shower Pan 4/18/2022 Approved JESUS RODRIGUEZ
Gas Test 6/9/2022 Approved RICHARD STEINBACH
ELECTRICAL-Final 1/25/2023 Corrections Issued HERBERT GIRON
Final 1/25/2023 Corrections Issued HERBERT GIRON
HVAC-Final 1/25/2023 Approved HERBERT GIRON
PLUMBING-Final 1/25/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/25/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 2/9/2023 Approved HERBERT GIRON
Final 2/9/2023 Permit Finaled HERBERT GIRON
Footing/Foundation/Slab 2/9/2023 Approved HERBERT GIRON
HVAC-Final 2/9/2023 Approved HERBERT GIRON
PLUMBING-Final 2/9/2023 Approved HERBERT GIRON
Smoke Detectors 2/9/2023 Approved HERBERT GIRON