4621 W 29TH ST 90016
Certificate Information: 4621 W 29TH ST 90016
- Application / Permit
- 21016-30000-01634
- Plan Check / Job No.
- B21WL00300
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage into an ADU per LAMC 12.22 A.33 (c)-(d) & per WFPP
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2021 | RICHARD GARCIA |
| Corrections Issued | 1/30/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/8/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/14/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 6/19/2021 | RICHARD GARCIA |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 2/2/2022 | STUART CHAPMAN |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2021 | THOMAS LANG |
| Sewer availability | Cleared | 2/25/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 5/6/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/13/2021 | Partial Approval | DAVID FEILER |
| Sewer | 7/13/2021 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 7/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/19/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 7/22/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/22/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/27/2021 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 8/3/2021 | Approved | CALEB MEISTER |
| Wood Frame | 8/3/2021 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 8/6/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| PLUMBING-Rough | 8/9/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/16/2021 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 8/16/2021 | Approved | STUART CHAPMAN |
| Insulation | 8/16/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | STUART CHAPMAN |
| Insulation | 8/17/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Approved | STUART CHAPMAN |
| Insulation | 8/23/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/30/2021 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/30/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 8/30/2021 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 9/1/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/1/2021 | Approved | STUART CHAPMAN |
| Final | 10/6/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 10/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 10/27/2021 | Corrections Issued | STUART CHAPMAN |
| Smoke Detectors | 10/27/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 11/9/2021 | Conditional Approval | STUART CHAPMAN |
| Smoke Detectors | 11/9/2021 | Approved | STUART CHAPMAN |
| Final | 2/1/2022 | OK to Issue CofO | STUART CHAPMAN |