164 N MARTEL AVE 90036
Certificate Information: 164 N MARTEL AVE 90036
- Application / Permit
- 21016-30000-01044
- Plan Check / Job No.
- B21WL00204
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion and addition of (E) garage to accessory dwelling unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | ALFREDO JARA |
| Corrections Issued | 1/29/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/14/2021 | JASON JANGADA |
| Applicant returned to address corrections | 8/26/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/16/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/5/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/9/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/18/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/3/2021 | MANUEL GARCIA |
| Plan Check Approved | 12/9/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 10/17/2022 | APPLICANT |
| Plan Check Approved | 11/16/2022 | RICHARD GARCIA |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 2/7/2025 | JOSE MACIAS |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 6/1/2021 | LOUIS ORTEGA |
| CPC | Cleared | 6/1/2021 | LOUIS ORTEGA |
| CPC | Cleared | 6/1/2021 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 6/1/2021 | LOUIS ORTEGA |
| HPOZ | Cleared | 6/3/2021 | DEEPEAKA DHALIWAL |
| Miscellaneous | Cleared | 6/3/2021 | DEEPEAKA DHALIWAL |
| ZI | Cleared | 6/3/2021 | DEEPEAKA DHALIWAL |
| Address approval | Cleared | 6/7/2021 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | JEREMY CHOK |
| Sewer availability | Cleared | 6/9/2021 | JEREMY CHOK |
| Hydrant and Access approval | Cleared | 7/5/2021 | ROBERT DUFF |
Contact Information
| Architect | Palmer,, Micheal Eugene; Lic. No.: C24051 | 3578 30TH STREET SAN DIEGO, CA 92104 |
| Architect | Verdugo,, Emilio Amado; Lic. No.: C33263 | 4324 GRANDVIEW BLVD LOS ANGELES, CA 90066 |
| Contractor | C K J Group; Lic. No.: 1021858-B | 19530 S NORMANDIE AVE TORRANCE, CA 90502 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 1/20/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/20/2023 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 3/13/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/6/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 4/6/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/6/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/6/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/18/2023 | Corrections Issued | RICHARD DOCKUS |
| Wood Frame | 4/18/2023 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/3/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 5/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 5/3/2023 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 5/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Wood Frame | 5/3/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/18/2023 | Approved | LILIANA PORTILLO |
| Insulation | 5/18/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/18/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/13/2023 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 6/21/2023 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 8/4/2023 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/19/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 9/19/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 9/19/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Final | 9/19/2023 | Approved | LILIANA PORTILLO |
| METHANE-Rough | 9/19/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 9/19/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 9/19/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 10/12/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/12/2023 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 10/16/2023 | Partial Inspection | DAVID FEILER |
| Pre-Inspection | 10/16/2023 | Partial Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/24/2023 | Approved | LILIANA PORTILLO |
| Final | 10/24/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 10/24/2023 | Approved | LILIANA PORTILLO |
| Final | 2/7/2025 | OK to Issue CofO | JOSE MACIAS |