3849 S BERRYMAN AVE 90066

Certificate Information: 3849 S BERRYMAN AVE 90066

Application / Permit
21016-30000-01018
Plan Check / Job No.
B21WL00194
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to accessory dwelling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 JASON JANGADA
Corrections Issued 1/23/2021 JASON JANGADA
Building Plans Picked Up 1/25/2021 APPLICANT
Applicant returned to address corrections 4/7/2021 JASON JANGADA
Applicant returned to address corrections 5/5/2021 JASON JANGADA
Plan Check Approved 5/7/2021 JASON JANGADA
Issued 5/11/2021 APPLICANT
CofO in Progress 6/14/2025 DAVID FEILER
CofO Issued 6/17/2025 RICHARD STEINBACH
Permit Finaled 6/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/16/2021 NIKTA MOUSAVI
Sewer availability Cleared 2/16/2021 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 2/18/2021 NIKTA MOUSAVI
Specific Plan Cleared 2/25/2021 FREDDY GARCIA
Construction near power lines Cleared 3/20/2021 RIDWAN HARDY

Contact Information

Contractor Bems Construction; Lic. No.: 1014009-B 2930 E 5TH ST APT #8      LONG BEACH, CA 90814
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/28/2021 Partial Approval ENRIQUE MIRELES
Pre-Inspection 5/28/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/3/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/31/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/31/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/31/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 8/31/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/3/2021 Approved ENRIQUE MIRELES
Wood Frame 9/3/2021 Approved ENRIQUE MIRELES
Insulation 9/8/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/8/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 9/15/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 9/15/2021 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 11/18/2021 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 11/18/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/9/2021 Approved ENRIQUE MIRELES
Final 12/9/2021 Corrections Issued ENRIQUE MIRELES
HVAC-Final 12/9/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/9/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/9/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/20/2021 Approved ENRIQUE MIRELES
Final 12/20/2021 Conditional Approval ENRIQUE MIRELES
HVAC-Final 12/20/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/20/2021 Approved ENRIQUE MIRELES
Final 12/22/2021 Corrections Issued ENRIQUE MIRELES
Final 6/14/2025 OK to Issue CofO DAVID FEILER