716 S WALKER AVE 1-8 90731
Certificate Information: 716 S WALKER AVE 1-8 90731
- Application / Permit
- 21016-30000-00728
- Plan Check / Job No.
- B21WL00142
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NON STRUCTURAL CONVERSION OF (E) 517 SF STORAGE RM INTO ADU
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | TARIK SAOUD |
| Corrections Issued | 1/25/2021 | TARIK SAOUD |
| Quality Review Completed | 2/3/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 8/29/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/8/2022 | APPLICANT |
| Plan Check Approved | 9/21/2022 | JOHN FRANCIA |
| Plan Check Approved | 9/21/2022 | MARILYN SEVILLA |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | JOEY BUCHANAN |
| Permit Finaled | 1/6/2023 | DAVID TSAU |
| CofO Issued | 1/6/2023 | DAVID TSAU |
| Permit Finaled | 1/6/2023 | DAVID TSAU |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/20/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 5/20/2021 | DENZEL HENDERSON |
| Address approval | Cleared | 4/21/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 4/21/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2022 | ERIK BEASLEY |
| Tenant Habitability Plan | Cleared | 6/21/2022 | MICHAEL SOTO |
| Green Code | Cleared | 7/7/2022 | RICHARD GARCIA |
Contact Information
| Architect | Medak,, Raymond; Lic. No.: C21755 | 2087 ASHBURY DRIVE CLEARWATER, FL 33764 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 9/28/2022 | No Access for Inspection | JOEY BUCHANAN |
| Green Building Final | 9/28/2022 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 9/28/2022 | Approved | JOEY BUCHANAN |
| Final | 12/22/2022 | Conditional Approval | JOEY BUCHANAN |