836 N TOYOPA DR 90272
Certificate Information: 836 N TOYOPA DR 90272
- Application / Permit
- 21016-30000-00709
- Plan Check / Job No.
- B21WL00133
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN EXISTING GARAGE INTO AN ADU
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | ALFREDO JARA |
| Corrections Issued | 2/23/2021 | ALFREDO JARA |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 4/12/2021 | RICHARD GARCIA |
| Plan Check Approved | 4/29/2021 | RICHARD GARCIA |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 3/29/2022 | ANDREW NAVE |
| CofO in Progress | 3/29/2022 | ANDREW NAVE |
| Permit Finaled | 4/4/2022 | DANIEL ORRANTE |
| CofO Issued | 4/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/12/2021 | KIRK LINKLATER |
| Address approval | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 4/4/2021 | ROBERT DUFF |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2021 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 6/25/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/30/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/30/2021 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 7/6/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 7/6/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 7/12/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 7/14/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 8/20/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 8/20/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 8/20/2021 | Approved | ANDREW NAVE |
| Wood Frame | 8/20/2021 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/27/2021 | Partial Inspection | ANDREW NAVE |
| Green Building Rough | 9/27/2021 | Partial Approval | ANDREW NAVE |
| Insulation | 10/1/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/1/2021 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 10/1/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/7/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 10/7/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 10/7/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 10/7/2021 | Approved | ANDREW NAVE |
| Shower Pan | 10/7/2021 | Approved | ANDREW NAVE |
| Gas Test | 11/4/2021 | Approved | ANDREW NAVE |
| Underground Mechanical | 11/4/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 3/8/2022 | Corrections Issued | ANDREW NAVE |
| Final | 3/8/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 3/8/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 3/8/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 3/8/2022 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 3/8/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 3/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 3/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 3/21/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 3/21/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 3/21/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/23/2022 | Approved | ANDREW NAVE |
| Final | 3/29/2022 | OK to Issue CofO | ANDREW NAVE |