10778 W CHALON ROAD 90077
Certificate Information: 10778 W CHALON ROAD 90077
- Application / Permit
- 21016-30000-00699
- Plan Check / Job No.
- B21WL00130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior and exterior alteration to (e) SFD to remodel kitchen and bathrooms, and repair (e) balcony water damaged framing
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/26/2022
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | REZA HAGHIGHAT |
| Corrections Issued | 1/25/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 2/4/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Plan Check Approved | 4/8/2021 | REZA HAGHIGHAT |
| Issued | 4/20/2021 | APPLICANT |
| Permit Finaled | 3/25/2022 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| ZA Case | Cleared | 2/9/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 2/12/2021 | KIRK LINKLATER |
Contact Information
| Architect | Holz,, Michael B; Lic. No.: C28082 | 12548 EVERGLADE STREET LOS ANGELES, CA 90066 |
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/13/2021 | Approved | CHRISTOPHER WILSON |
| Underground Mechanical | 5/13/2021 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/10/2021 | Corrections Issued | MATT KELLERMAN |
| HVAC-Rough | 6/10/2021 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Rough | 6/16/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 6/17/2021 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/6/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 7/6/2021 | Partial Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 7/8/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/8/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 7/8/2021 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/9/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 7/9/2021 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 7/20/2021 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/28/2021 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 7/28/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/9/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 9/20/2021 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Final | 2/28/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/3/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 3/3/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 3/4/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/9/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/16/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 3/17/2022 | Approved | CHRISTOPHER WILSON |
| Final | 3/25/2022 | Permit Finaled | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 3/25/2022 | Approved | CHRISTOPHER WILSON |