18355 W COLLINS ST #65 91356
Certificate Information: 18355 W COLLINS ST #65 91356
- Application / Permit
- 21016-30000-00692
- Plan Check / Job No.
- B21WL00127
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT PORTION OF (E) RECREATION ROOM INTO A 2 BEDROOM ADU PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | RICHARD GARCIA |
| Corrections Issued | 1/17/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 12/27/2021 | JASON JANGADA |
| Plan Check Approved | 1/10/2022 | RICHARD GARCIA |
| Issued | 4/1/2022 | APPLICANT |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | JEFFREY FULTON |
| Permit Finaled | 2/27/2023 | JEFFREY DURAN |
| CofO Issued | 2/27/2023 | JEFFREY DURAN |
| Permit Finaled | 2/27/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | ADRIAN CASTRO |
| Tenant Habitability Plan | Cleared | 12/14/2021 | RICHARD BRINSON |
Contact Information
| Contractor | Rigid Design & Construction Inc; Lic. No.: 947498-B | 16501 VENTURA BLVD. STE 400 ENCINO, CA 91436 |
| Engineer | Kamkar,, Albert; Lic. No.: C38311 | 12340 SANTA MONICA BLVD 236 SANTA MONICA, CA 90025 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 8/9/2022 | Corrections Issued | JEFFREY FULTON |
| Wood Frame | 10/5/2022 | Partial Inspection | JEFFREY FULTON |
| Insulation | 10/18/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 10/18/2022 | Approved | DANIEL VARNUM |
| Drywall Nailing | 11/15/2022 | Approved | DANIEL VARNUM |
| Drywall Nailing | 11/17/2022 | Approved | DANIEL VARNUM |
| Final | 1/27/2023 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 1/27/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 2/22/2023 | OK to Issue CofO | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 2/22/2023 | Approved | JEFFREY FULTON |
| Special/Order Compliance | 2/22/2023 | Conditional Approval | STEVEN LEVITT |