1539 S BELOIT AVE 106 & 219 90025

Certificate Information: 1539 S BELOIT AVE 106 & 219 90025

Application / Permit
21016-30000-00432
Plan Check / Job No.
B21WL00094
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert 2 recreation rooms into 2 ADUs. Proposed unit 106 @ first floor Proposed unit 219 @ second floor
Permit Issued
Issued on 12/16/2021
Issuing Office
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 TARIK SAOUD
Corrections Issued 1/25/2021 TARIK SAOUD
Quality Review Completed 2/4/2021 CHIHARU SUZUKI
Disabled Access Plans Picked Up 10/12/2021 APPLICANT
Plan Check Approved 12/9/2021 TARIK SAOUD
Building Plans Picked Up 12/10/2021 APPLICANT
Issued 12/16/2021 APPLICANT
CofO in Progress 4/12/2023 SORIN CIRSTOIU
Permit Finaled 4/12/2023 DAVID TSAU
CofO Issued 4/12/2023 DAVID TSAU
Permit Finaled 4/12/2023 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 6/16/2021 JASON CHAN
Miscellaneous Cleared 6/16/2021 JASON CHAN
ZA Case Cleared 6/16/2021 JASON CHAN
Tenant Habitability Plan Cleared 9/1/2021 MICHAEL SOTO
Specific Plan Cleared 9/22/2021 PEDRO AYALA
Fire Marshal Fire Life Safety Cleared 9/30/2021 MENOA AGHAJANI
DAS Clearance Cleared 11/17/2021 TARIK SAOUD

Contact Information

Contractor Owner-Builder       ,
Engineer Cohanzad,, Isaac Wise; Lic. No.: C39474 11601 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2022 Approved JOHN DODGE
Wood Frame 4/4/2022 Not Ready for Inspection JOHN DODGE
Wood Frame 5/18/2022 Not Ready for Inspection JOHN DODGE
Wood Frame 5/23/2022 Partial Approval JOHN DODGE
Drywall Nailing 6/1/2022 Corrections Issued SORIN CIRSTOIU
Interior/Exterior Lathing 6/1/2022 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 8/26/2022 Partial Inspection SORIN CIRSTOIU
Wood Frame 9/12/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 9/20/2022 Partial Approval ALAN NOVAK
Interior/Exterior Lathing 9/22/2022 Partial Approval ALAN NOVAK
Insulation 10/3/2022 No Access for Inspection PAUL DAVIDSON
Wood Frame 10/3/2022 No Access for Inspection PAUL DAVIDSON
Insulation 10/6/2022 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 10/6/2022 Not Ready for Inspection PAUL DAVIDSON
Insulation 10/17/2022 Approved PAUL DAVIDSON
Wood Frame 10/17/2022 Approved PAUL DAVIDSON
Drywall Nailing 10/24/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 10/24/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 11/15/2022 Partial Approval SORIN CIRSTOIU
Final 3/24/2023 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Final 3/24/2023 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 3/24/2023 Not Ready for Inspection SORIN CIRSTOIU
Final 4/5/2023 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Final 4/5/2023 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 4/5/2023 Not Ready for Inspection SORIN CIRSTOIU
Final 4/11/2023 Not Ready for Inspection SORIN CIRSTOIU
Smoke Detectors 4/11/2023 Not Ready for Inspection SORIN CIRSTOIU
Final 4/12/2023 Conditional Approval SORIN CIRSTOIU