8033 S HANDLEY AVE 90045

Certificate Information: 8033 S HANDLEY AVE 90045

Application / Permit
21016-30000-00422
Plan Check / Job No.
B21WL00090
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) attached 2-car garage on a one-story SFD into a JR ADU.
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 RICHARD GARCIA
Corrections Issued 1/24/2021 RICHARD GARCIA
Applicant returned to address corrections 5/4/2021 RICHARD GARCIA
Applicant returned to address corrections 7/13/2021 RICHARD GARCIA
Applicant returned to address corrections 7/21/2021 MANUEL GARCIA
Plan Check Approved 8/6/2021 CHIHARU SUZUKI
Issued 8/6/2021 APPLICANT
CofO in Progress 3/8/2022 BOBBY KEY
CofO Issued 3/22/2022 DANIEL ORRANTE
Permit Finaled 3/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/1/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/1/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/2/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 6/7/2021 BRIAN MILLER
Specific Plan Cleared 6/15/2021 LOUIS ORTEGA
ZI Cleared 6/15/2021 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/20/2021 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 10/26/2021 Partial Approval BOBBY KEY
Footing/Foundation/Slab 11/10/2021 Approved DAVID FEILER
ELECTRICAL-Rough 12/7/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 1/12/2022 Partial Approval BOBBY KEY
Gas Test 1/12/2022 Approved BOBBY KEY
HVAC-Rough 1/12/2022 Approved BOBBY KEY
PLUMBING-Rough 1/12/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/19/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Approved BOBBY KEY
Green Building Rough 1/19/2022 Approved BOBBY KEY
Insulation 1/19/2022 Approved BOBBY KEY
METHANE-Rough 1/19/2022 Approved BOBBY KEY
Drywall Nailing 1/26/2022 Approved BOBBY KEY
Final 1/26/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 1/26/2022 Approved BOBBY KEY
Shower Pan 1/26/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/8/2022 Approved BOBBY KEY
Final 3/8/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 3/8/2022 Approved BOBBY KEY
PLUMBING-Final 3/8/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 3/8/2022 Approved BOBBY KEY