3576 N DOVER ST 90039
Certificate Information: 3576 N DOVER ST 90039
- Application / Permit
- 21016-20002-21076
- Plan Check / Job No.
- B22VN14251
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO 21016-10000-21076 TO CORRECT SCOPE OF WORK TO ADD 7'-6" X 15'-0" ADDITION TO AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TO CORRECT THE STRUCTURAL INVENTORY - PER ENGINEER
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2022 | SERGIO MUNIZ |
| Corrections Issued | 9/26/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 12/5/2022 | APPLICANT |
| Applicant returned to address corrections | 7/19/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/3/2023 | OMAR GARNICA |
| Issued | 10/3/2023 | APPLICANT |
| Permit Finaled | 7/17/2024 | COREY HUPP |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 9/22/2023 | STEVEN JIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Final | 1/12/2024 | Not Ready for Inspection | COREY HUPP |
| Final | 2/16/2024 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | COREY HUPP |
| Final | 7/17/2024 | Permit Finaled | COREY HUPP |
| Footing/Foundation/Slab | 7/17/2024 | Approved | COREY HUPP |
| Green Building Final | 7/17/2024 | Approved | COREY HUPP |
| Green Building Rough | 7/17/2024 | Approved | COREY HUPP |
| Smoke Detectors | 7/17/2024 | Approved | COREY HUPP |