2240 W EWING ST 90039

Certificate Information: 2240 W EWING ST 90039

Application / Permit
21016-20001-54867
Plan Check / Job No.
B22VN00562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPL. PERMIT TO 21016-20000-54867 TO ENCLOSE THE REAR PATIO (480 SQFT) AND A PORTION OF THE FRONT PATIO (100 SQFT) AND ADD A DECK W/ INTERIOR REMODEL
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 PETER MOSESIAN
Corrections Issued 1/28/2022 PETER MOSESIAN
Building Plans Picked Up 2/3/2022 APPLICANT
Issued 3/30/2022 APPLICANT
CofO in Progress 8/1/2022 THOMAS LOGRASSO
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/3/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/3/2022 TREVOR QUAN
Sewer availability Cleared 2/3/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul H; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 4/13/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 4/13/2022 Partial Approval THOMAS LOGRASSO
HVAC-Rough 4/13/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 4/13/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 4/25/2022 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 4/25/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 6/6/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 6/9/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 6/9/2022 Partial Approval THOMAS LOGRASSO
Insulation 6/9/2022 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/9/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 6/16/2022 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/21/2022 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/23/2022 Approved STUART CHAPMAN
Final 7/20/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 7/20/2022 Approved THOMAS LOGRASSO
Green Building Final 7/20/2022 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 7/20/2022 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 7/20/2022 Approved THOMAS LOGRASSO
Final 8/1/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 8/1/2022 Approved THOMAS LOGRASSO
MERV13>=Final 8/1/2022 Approved THOMAS LOGRASSO