7840 S DALTON AVE 90047
Certificate Information: 7840 S DALTON AVE 90047
- Application / Permit
- 21016-20001-12979
- Plan Check / Job No.
- B21VN11979
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPL. PERMIT TO 21016-20000-12979 TO PROVIDE NEW FOOTING AND UNDERPINNING ON (E) FOUNDATION. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | LUISANGEL VALENZUELA |
| Issued | 9/3/2021 | APPLICANT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Permit Finaled | 10/20/2021 | JOAQUIN GREENOUGH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hi-Tech Builders Inc; Lic. No.: 957111-B | 5435 BALBOA BLVD STE 200 ENCINO, CA 91316 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2021 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 9/22/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/28/2021 | Not Ready for Inspection | HORACE FULTZ |
| Footing/Foundation/Slab | 9/30/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/5/2021 | Partial Approval | FREDDIE RIVERA |
| Final | 10/20/2021 | Permit Finaled | JOAQUIN GREENOUGH |