9109 W OLIN ST 90034

Certificate Information: 9109 W OLIN ST 90034

Application / Permit
21016-20001-07773
Plan Check / Job No.
B21VN15940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 21016-20000-07773 TO REVISE THE FOUNDATION PLANS AND ADD 14'-9" X 19 IRREGULAR SHAPE TO ENLARGE ADU. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
Permit Finaled on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 RAPHAEL ROSAS
Corrections Issued 11/27/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/30/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/4/2022 RAPHAEL ROSAS
Applicant returned to address corrections 2/24/2022 RAPHAEL ROSAS
Plan Check Approved 3/23/2022 RAPHAEL ROSAS
Issued 4/1/2022 APPLICANT
Building Plans Picked Up 4/8/2022 APPLICANT
Permit Finaled 11/17/2022 JESUS RODRIGUEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/11/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/17/2022 WALLIE JONG
Sewer availability Cleared 2/17/2022 WALLIE JONG
Construction near power lines Cleared 2/24/2022 JOHN BACON
Grading Pre-Inspection Cleared 3/8/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 6250 CANOGA AVE #525      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2022 Approved EVAN COOPER
Footing/Foundation/Slab 4/12/2022 Partial Approval EVAN COOPER
METHANE-Barrier 4/12/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 4/12/2022 Not Ready for Inspection EVAN COOPER
Sewer 4/25/2022 Corrections Issued EVAN COOPER
Sewer 4/26/2022 Approved EVAN COOPER
Wood Frame 4/26/2022 Partial Approval EVAN COOPER
METHANE-Subgrade 4/28/2022 Approved EVAN COOPER
PLUMBING-Rough 4/28/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/10/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 5/10/2022 Corrections Issued EVAN COOPER
Wood Frame 5/10/2022 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 5/20/2022 Approved EVAN COOPER
ELECTRICAL-Rough 5/20/2022 Approved EVAN COOPER
Green Building Rough 5/20/2022 Approved EVAN COOPER
HVAC-Rough 5/20/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/20/2022 Partial Approval EVAN COOPER
METHANE-Rough 5/20/2022 Approved EVAN COOPER
PLUMBING-Rough 5/20/2022 Approved EVAN COOPER
Insulation 5/23/2022 Corrections Issued EVAN COOPER
Drywall Nailing 5/27/2022 Approved EVAN COOPER
Insulation 5/27/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/9/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 6/16/2022 Approved EVAN COOPER
Shower Pan 6/16/2022 Approved EVAN COOPER
ELECTRICAL-Final 8/26/2022 Corrections Issued ANDREW NAVE
Final 8/26/2022 Corrections Issued ANDREW NAVE
Green Building Final 8/26/2022 Corrections Issued ANDREW NAVE
HVAC-Final 8/26/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 8/26/2022 Corrections Issued ANDREW NAVE
Smoke Detectors 8/26/2022 Approved ANDREW NAVE
Footing/Foundation/Slab 9/21/2022 Approved EVAN COOPER
METHANE-Barrier 9/21/2022 Approved EVAN COOPER
Final 10/26/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/26/2022 Approved JESUS RODRIGUEZ
Final 11/17/2022 Permit Finaled JESUS RODRIGUEZ