10250 N WOODWARD AVE 91040

Certificate Information: 10250 N WOODWARD AVE 91040

Application / Permit
21016-20001-05024
Plan Check / Job No.
B21VN15183
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPL. PERMIT TO 21016-20000-05024 TO REVISE FLOOR PLAN AND REVISE PROPOSED ADDITION FROM 10'-1" X 11'-7" TO 13'-1" X 11'-7".
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
Permit Finaled on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 JEROME MAGAT PALMA
Plan Check Approved 11/7/2021 JEROME MAGAT PALMA
Issued 11/8/2021 APPLICANT
Building Plans Picked Up 11/9/2021 APPLICANT
Permit Finaled 12/22/2022 DAVID ANDERSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/9/2021 Approved WILLIAM KUEHN
Underground Mechanical 12/9/2021 Partial Inspection WILLIAM KUEHN
ELECTRICAL-Rough 12/30/2021 Partial Approval MATTHEW NELSON
PLUMBING-Rough 12/30/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/7/2022 Partial Approval JOHN HAYES
HVAC-Rough 1/13/2022 Approved MATTHEW NELSON
Wood Frame 1/19/2022 Not Ready for Inspection MICHEL ABAJAN
Insulation 1/24/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 1/24/2022 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 2/16/2022 Approved GREGG CUMMINGS
Green Building Rough 2/16/2022 Approved GREGG CUMMINGS
Insulation 2/16/2022 Approved GREGG CUMMINGS
Final 5/10/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
Final 7/15/2022 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 7/15/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Final 7/15/2022 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 7/15/2022 Approved DAVID ANDERSON
Final 9/23/2022 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 9/23/2022 Approved DAVID ANDERSON
Green Building Final 9/23/2022 Approved DAVID ANDERSON
Final 12/13/2022 Not Ready for Inspection DAVID ANDERSON