249 N LADERA DR 90210
Certificate Information: 249 N LADERA DR 90210
- Application / Permit
- 21016-20001-01081
- Plan Check / Job No.
- B22VN04443
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- SUPPL. PERMIT TO 21016-20000-01081 TO ADD A NEW STORAGE w/ RETAINING WALL AND PATIO COVER NEXT TO THE (E) POOL.
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/23/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/15/2022 | MOHAMMAD ESMAILI |
| Issued | 4/15/2022 | APPLICANT |
| Permit Finaled | 10/20/2022 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/23/2022 | MOHAMMAD ESMAILI |
| Roof/Waste drainage to street | Cleared | 4/9/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | STEVEN JIN |
Contact Information
| Contractor | L D L General Contractors Inc; Lic. No.: 856503-B | 7216 LITTLER COURT MOORPARK, CA 93021 |
| Engineer | Vlachos,, Manuel Vassilios; Lic. No.: C64976 | 6832 RIDGEMARK DR MOORPARK, CA 93021 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/20/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/25/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 6/9/2022 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 6/9/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 6/9/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/13/2022 | Approved | CHRISTOPHER WILSON |
| Final | 6/13/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/13/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 6/14/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 6/14/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 6/22/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/22/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/29/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | CHRISTOPHER WILSON |
| Final | 10/20/2022 | Permit Finaled | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/20/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 10/20/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 10/20/2022 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 10/20/2022 | Approved | CHRISTOPHER WILSON |