13484 W BAYLISS ROAD 90049
Certificate Information: 13484 W BAYLISS ROAD 90049
- Application / Permit
- 21016-20000-59422
- Plan Check / Job No.
- B21VN18145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) FIRST AND SECOND FLOOR. (N) ROOF STRUCTURE OVER (E) FIRST FLOOR
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/23/2024
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/10/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Plan Check Approved | 5/16/2022 | MOHAMMAD ESMAILI |
| Issued | 5/24/2022 | APPLICANT |
| Permit Finaled | 8/23/2024 | KEVIN SARGSYAN |
Permit Application Clearance Information
| ZA Case | Cleared | 2/14/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/17/2022 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 2/24/2022 | VASIL MIHALEV |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
| Distance to fire station | Cleared | 4/22/2022 | CINDY JOSSELYN |
| Roof/Waste drainage to street | Cleared | 4/27/2022 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 5/19/2022 | CHRIS VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/26/2022 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 9/27/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/28/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/30/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/3/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 10/3/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/4/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 10/21/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Corrections Issued | JUAN VALENZUELA |
| Deputy Wood Construction | 12/1/2022 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/14/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 2/14/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/14/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 2/16/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/22/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/22/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 2/24/2023 | Approved | KENNETH NAGLE |
| Shower Pan | 2/24/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 3/1/2023 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 3/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| Drywall Nailing | 3/3/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/3/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 3/3/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Final | 8/7/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 8/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 8/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 8/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/19/2024 | Approved | KEVIN SARGSYAN |
| Final | 8/19/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 8/19/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 8/19/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 8/19/2024 | Approved | KEVIN SARGSYAN |
| Final | 8/23/2024 | Permit Finaled | KEVIN SARGSYAN |
| HVAC-Final | 8/23/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 8/23/2024 | Approved | KEVIN SARGSYAN |