6754 N SYLVIA AVE 91335

Certificate Information: 6754 N SYLVIA AVE 91335

Application / Permit
21016-20000-59362
Plan Check / Job No.
B21VN18106
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT(E) 20' X 32' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
CofO Issued on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2022 RAPHAEL ROSAS
Corrections Issued 1/17/2022 RAPHAEL ROSAS
Building Plans Picked Up 1/19/2022 APPLICANT
Plan Check Approved 4/25/2022 MOHAMMAD ESMAILI
Issued 7/1/2022 APPLICANT
CofO in Progress 12/12/2022 JEFFREY BULL
CofO Issued 12/22/2022 MICHAEL SMITH
Permit Finaled 12/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/2/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/2/2022 JOSE DUARTE-DIAZ
ZI Cleared 3/2/2022 DANG NGUYEN

Contact Information

Contractor Martillos General Construction Co; Lic. No.: 1060708-B 20511 NAPA ST      WINNETKA, CA 91306
Engineer Chamberlain,, Robert Douglas; Lic. No.: C67937 7235 DE CELIS PL      VAN NUYS, CA 91406

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2022 Approved SEAN HAUPT
Underground Mechanical 8/24/2022 Approved SEAN HAUPT
Deputy Drilled-In Anchors 8/29/2022 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 8/30/2022 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 9/8/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 9/29/2022 Approved JEFFREY BULL
HVAC-Rough 9/29/2022 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 9/29/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/5/2022 Approved TROY SANDERS
Green Building Rough 10/5/2022 Approved TROY SANDERS
HVAC-Rough 10/5/2022 Conditional Approval TROY SANDERS
Interior/Exterior Lathing 10/5/2022 Partial Approval TROY SANDERS
Insulation 10/7/2022 Approved MORRIS JACKSON
Drywall Nailing 10/13/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 11/18/2022 Approved JEFFREY BULL
Final 11/18/2022 Not Ready for Inspection JEFFREY BULL
HVAC-Final 11/18/2022 Approved JEFFREY BULL
PLUMBING-Final 11/18/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 11/18/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 11/18/2022 Approved JEFFREY BULL
Final 12/12/2022 OK to Issue CofO JEFFREY BULL