8205-8207 N LURLINE AVE 91306

Certificate Information: 8205-8207 N LURLINE AVE 91306

Application / Permit
21016-20000-59338
Plan Check / Job No.
B21VN18092
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
CofO Issued on 4/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2022 ARTIN ZARUKIAN
Corrections Issued 1/15/2022 ARTIN ZARUKIAN
Building Plans Picked Up 1/20/2022 APPLICANT
Plan Check Approved 9/16/2022 YAQUB MIRZA
Issued 9/16/2022 APPLICANT
CofO in Progress 4/11/2023 SEAN HAUPT
Permit Finaled 4/13/2023 JOHN JANSON
CofO Issued 4/13/2023 JOHN JANSON
Permit Finaled 4/13/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/24/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/24/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/24/2022 JOSE DUARTE-DIAZ
Miscellaneous Cleared 2/7/2022 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/7/2022 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 10/13/2022 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 10/27/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Approved STEVEN BACK
Footing/Foundation/Slab 10/27/2022 Approved STEVEN BACK
ELECTRICAL-Rough 12/21/2022 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 12/21/2022 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 12/21/2022 Approved ALEXANDER HANDY
Insulation 1/3/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 1/19/2023 Approved ALEXANDER HANDY
Insulation 1/19/2023 Approved ALEXANDER HANDY
Drywall Nailing 2/2/2023 Corrections Issued JESUS PINEDA
Green Building Rough 2/2/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 2/2/2023 Approved JESUS PINEDA
Drywall Nailing 2/7/2023 Approved ALEXANDER HANDY
HVAC-Rough 2/7/2023 Approved ALEXANDER HANDY
Wood Frame 2/7/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/8/2023 Approved ALEXANDER HANDY
Final 3/24/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 3/24/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 3/24/2023 No Access for Inspection ALEXANDER HANDY
Final 4/10/2023 OK to Issue CofO SEAN HAUPT
Green Building Final 4/10/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Approved SEAN HAUPT
Service/Power Release 4/10/2023 Approved SEAN HAUPT
Smoke Detectors 4/10/2023 Approved SEAN HAUPT