7649 N GENESTA AVE 91406

Certificate Information: 7649 N GENESTA AVE 91406

Application / Permit
21016-20000-59211
Plan Check / Job No.
B21VN18001
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 JEROME MAGAT PALMA
Corrections Issued 1/13/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 2/6/2022 JEROME MAGAT PALMA
Plan Check Approved 2/17/2022 JEROME MAGAT PALMA
Building Plans Picked Up 2/18/2022 APPLICANT
Issued 3/1/2022 APPLICANT
CofO in Progress 6/28/2022 ALAN MORELOS
CofO Issued 8/31/2022 MICHAEL SMITH
Permit Finaled 8/31/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/10/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/10/2022 CARLOS AGUILERA
Sewer availability Cleared 2/10/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2022 Approved RAUL OLAGI
PLUMBING-Rough 3/21/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/23/2022 Approved RAUL OLAGI
PLUMBING-Rough 3/23/2022 Partial Approval RAUL OLAGI
Underground Mechanical 3/23/2022 Partial Approval RAUL OLAGI
Underground Mechanical 3/31/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 4/29/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 4/29/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/5/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/5/2022 Approved RAUL OLAGI
HVAC-Rough 5/5/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/5/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 5/5/2022 Approved RAUL OLAGI
Deputy Wood Construction 5/20/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/23/2022 Partial Approval RAUL OLAGI
Green Building Rough 5/23/2022 Approved RAUL OLAGI
Insulation 5/23/2022 Approved RAUL OLAGI
Sewer 5/23/2022 Not Ready for Inspection RAUL OLAGI
Sewer 6/1/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 6/14/2022 Approved ALAN MORELOS
ELECTRICAL-Final 6/14/2022 Corrections Issued ALAN MORELOS
Final 6/14/2022 Corrections Issued ALAN MORELOS
Green Building Final 6/14/2022 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved ALAN MORELOS
Smoke Detectors 6/14/2022 Not Ready for Inspection ALAN MORELOS
Final 6/22/2022 Corrections Issued ALAN MORELOS
Green Building Final 6/22/2022 Not Ready for Inspection ALAN MORELOS
Smoke Detectors 6/22/2022 Approved ALAN MORELOS
ELECTRICAL-Final 6/27/2022 Approved ALAN MORELOS
Final 6/27/2022 OK to Issue CofO ALAN MORELOS
Green Building Final 6/27/2022 Approved ALAN MORELOS
HVAC-Final 6/27/2022 Approved ALAN MORELOS
PLUMBING-Final 6/27/2022 Approved ALAN MORELOS