7649 N GENESTA AVE 91406
Certificate Information: 7649 N GENESTA AVE 91406
- Application / Permit
- 21016-20000-59211
- Plan Check / Job No.
- B21VN18001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 1/13/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/6/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/17/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Issued | 3/1/2022 | APPLICANT |
| CofO in Progress | 6/28/2022 | ALAN MORELOS |
| CofO Issued | 8/31/2022 | MICHAEL SMITH |
| Permit Finaled | 8/31/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/10/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/23/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/23/2022 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 3/23/2022 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 3/31/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/29/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/5/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/5/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/5/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/5/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/5/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 5/23/2022 | Approved | RAUL OLAGI |
| Insulation | 5/23/2022 | Approved | RAUL OLAGI |
| Sewer | 5/23/2022 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 6/1/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 6/14/2022 | Corrections Issued | ALAN MORELOS |
| Final | 6/14/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Final | 6/14/2022 | Not Ready for Inspection | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 6/14/2022 | Not Ready for Inspection | ALAN MORELOS |
| Final | 6/22/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Final | 6/22/2022 | Not Ready for Inspection | ALAN MORELOS |
| Smoke Detectors | 6/22/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 6/27/2022 | Approved | ALAN MORELOS |
| Final | 6/27/2022 | OK to Issue CofO | ALAN MORELOS |
| Green Building Final | 6/27/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 6/27/2022 | Approved | ALAN MORELOS |
| PLUMBING-Final | 6/27/2022 | Approved | ALAN MORELOS |