7540 N FIRMAMENT AVE 91406

Certificate Information: 7540 N FIRMAMENT AVE 91406

Application / Permit
21016-20000-59155
Plan Check / Job No.
B21VN17958
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 SERGIO MUNIZ
Corrections Issued 2/6/2022 SERGIO MUNIZ
Applicant returned to address corrections 7/21/2022 SERGIO MUNIZ
Building Plans Picked Up 7/22/2022 APPLICANT
Applicant returned to address corrections 9/27/2022 GEORGE ALVAREZ
Plan Check Approved 11/3/2022 VICTOR CHEN
Issued 11/18/2022 APPLICANT
CofO in Progress 10/4/2023 GREGG CUMMINGS
CofO Issued 11/16/2023 RUBEN SALAS
Permit Finaled 11/16/2023 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 4/12/2022 RIDWAN HARDY
Address approval Cleared 5/20/2022 LEE GUILBEAUX
Sewer availability Cleared 5/20/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/20/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/21/2022 LEE GUILBEAUX

Contact Information

Contractor Treeium Inc; Lic. No.: 617148-B 5352 LAUREL CANYON BLVD #200      VALLEY VILLAGE, CA 91607
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/1/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 12/8/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 12/8/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 12/8/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/13/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval CHRISTOPHER DELLEFIELD
MERV13>=Rough 1/20/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/13/2023 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/13/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 2/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/13/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/13/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 2/13/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 2/23/2023 Corrections Issued MATTHEW NELSON
Shower Pan 2/23/2023 Approved MATTHEW NELSON
Insulation 3/7/2023 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/13/2023 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/13/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 7/5/2023 Corrections Issued MATTHEW NELSON
MERV13>=Final 7/5/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 7/5/2023 Approved MATTHEW NELSON
Final 7/14/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Not Ready GREGG CUMMINGS
Final 7/26/2023 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved GREGG CUMMINGS
Final 9/12/2023 Corrections Issued GREGG CUMMINGS
Final 9/28/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Final 10/3/2023 Approved GREGG CUMMINGS
Final 10/3/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/3/2023 Approved GREGG CUMMINGS
PLUMBING-Final 10/3/2023 Approved GREGG CUMMINGS