7540 N FIRMAMENT AVE 91406
Certificate Information: 7540 N FIRMAMENT AVE 91406
- Application / Permit
- 21016-20000-59155
- Plan Check / Job No.
- B21VN17958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | SERGIO MUNIZ |
| Corrections Issued | 2/6/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/21/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/22/2022 | APPLICANT |
| Applicant returned to address corrections | 9/27/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 11/3/2022 | VICTOR CHEN |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 10/4/2023 | GREGG CUMMINGS |
| CofO Issued | 11/16/2023 | RUBEN SALAS |
| Permit Finaled | 11/16/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/12/2022 | RIDWAN HARDY |
| Address approval | Cleared | 5/20/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/20/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/20/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 12/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 12/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/13/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 1/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/13/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/13/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/13/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/13/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 2/23/2023 | Corrections Issued | MATTHEW NELSON |
| Shower Pan | 2/23/2023 | Approved | MATTHEW NELSON |
| Insulation | 3/7/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/13/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 7/5/2023 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 7/5/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 7/5/2023 | Approved | MATTHEW NELSON |
| Final | 7/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Approved | GREGG CUMMINGS |
| Final | 9/12/2023 | Corrections Issued | GREGG CUMMINGS |
| Final | 9/28/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/3/2023 | Approved | GREGG CUMMINGS |
| Final | 10/3/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 10/3/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/3/2023 | Approved | GREGG CUMMINGS |