12207 W GOSHEN AVE 90049

Certificate Information: 12207 W GOSHEN AVE 90049

Application / Permit
21016-20000-59030
Plan Check / Job No.
B21VN17909
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 45 SF PORTION OF EX. GARAGE AND CONVERT 11.6" x 18.3" TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/9/2022
Issuing Office
Current Status
CofO Issued on 6/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 JEFFREY TANGONAN
Corrections Issued 1/22/2022 JEFFREY TANGONAN
Applicant returned to address corrections 3/24/2022 JEFFREY TANGONAN
Issued 4/9/2022 APPLICANT
Building Plans Picked Up 4/20/2022 APPLICANT
CofO in Progress 6/3/2022 OGANES TARAKHCHYAN
Permit Finaled 6/27/2022 DANIEL ORRANTE
CofO Issued 6/27/2022 DANIEL ORRANTE
Permit Finaled 6/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2022 JENSON LEE
Sewer availability Cleared 3/1/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/8/2022 OSCAR GUTIERREZ
Construction near power lines Cleared 3/10/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/29/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/29/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/29/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 4/29/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/29/2022 Approved OGANES TARAKHCHYAN
Insulation 5/6/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/6/2022 Approved OGANES TARAKHCHYAN
Shower Pan 5/6/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/9/2022 Approved OGANES TARAKHCHYAN
Green Building Final 5/24/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 5/24/2022 Approved OGANES TARAKHCHYAN
Final 6/3/2022 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 6/3/2022 Approved OGANES TARAKHCHYAN