12207 W GOSHEN AVE 90049
Certificate Information: 12207 W GOSHEN AVE 90049
- Application / Permit
- 21016-20000-59030
- Plan Check / Job No.
- B21VN17909
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 45 SF PORTION OF EX. GARAGE AND CONVERT 11.6" x 18.3" TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/9/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | JEFFREY TANGONAN |
| Corrections Issued | 1/22/2022 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 3/24/2022 | JEFFREY TANGONAN |
| Issued | 4/9/2022 | APPLICANT |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| CofO in Progress | 6/3/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/27/2022 | DANIEL ORRANTE |
| CofO Issued | 6/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | JENSON LEE |
| Sewer availability | Cleared | 3/1/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | OSCAR GUTIERREZ |
| Construction near power lines | Cleared | 3/10/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/6/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/6/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/6/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/9/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 5/24/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/24/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 6/3/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/3/2022 | Approved | OGANES TARAKHCHYAN |