3946 W EDENHURST AVE 90039
Certificate Information: 3946 W EDENHURST AVE 90039
- Application / Permit
- 21016-20000-58877
- Plan Check / Job No.
- B21VN17822
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DET 20'X20' GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER ENGR.
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 1/8/2022 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/26/2022 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/5/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/28/2022 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 6/13/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 7/12/2022 | HAYATO TSUCHIYA |
| Issued | 7/12/2022 | APPLICANT |
| Building Plans Picked Up | 7/22/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/31/2023 | RONALD MYRICK |
| CofO Issued | 8/31/2023 | RONALD MYRICK |
| Permit Finaled | 8/31/2023 | RONALD MYRICK |
Permit Application Clearance Information
| ZI | Cleared | 2/8/2022 | RICHARD REASER |
| Address approval | Cleared | 2/9/2022 | WALLIE JONG |
| Permit | Cleared | 2/9/2022 | WALLIE JONG |
| Sewer availability | Cleared | 2/9/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 5/19/2022 | RIDWAN HARDY |
| Construction near power lines | Cleared | 5/19/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/17/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/17/2022 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/17/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/1/2022 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 12/1/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 12/1/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/7/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/7/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/15/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/30/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/1/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/10/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/10/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/24/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |