222 S MCCADDEN PL 90004

Certificate Information: 222 S MCCADDEN PL 90004

Application / Permit
21016-20000-58821
Plan Check / Job No.
B21VN13652
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
CONVERT EXISTING DETACHED 3 CAR GARAGE (426 SQFT) INTO 1 CAR CARPORT (332 SQFT)
Permit Issued
Issued on 11/15/2022
Issuing Office
Current Status
Issued on 11/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 PETER MOSESIAN
Corrections Issued 10/23/2021 PETER MOSESIAN
Quality Review Completed 10/29/2021 OMID HEDAYAT
Building Plans Picked Up 11/2/2021 APPLICANT
Applicant returned to address corrections 3/30/2022 PETER MOSESIAN
Applicant returned to address corrections 9/16/2022 PETER MOSESIAN
Plan Check Approved 11/10/2022 PETER MOSESIAN
Issued 11/15/2022 APPLICANT

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 10/19/2022 DEEPEAKA DHALIWAL
HPOZ Cleared 10/19/2022 DEEPEAKA DHALIWAL

Contact Information

Contractor David Elliot Builders Inc; Lic. No.: 1021000-B 5967 W 3RD ST #360      LOS ANGELES, CA 90036
Engineer Mercado,, Lizandro; Lic. No.: S4331 27240 TURNBERRY LN STE 200      VALENCIA, CA 91355

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2024 Approved RONNIE MINDANAO
Deputy Other (see comments) 12/16/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval RONNIE MINDANAO
Green Building Rough 1/13/2025 Not Ready for Inspection RONNIE MINDANAO
Deputy Methane Barrier 1/16/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Approved RONNIE MINDANAO
Green Building Rough 1/16/2025 Approved RONNIE MINDANAO
METHANE-Barrier 1/16/2025 Approved RONNIE MINDANAO
METHANE-Final 1/16/2025 Approved RONNIE MINDANAO
METHANE-Rough 1/16/2025 Approved RONNIE MINDANAO
METHANE-Subgrade 1/16/2025 Approved RONNIE MINDANAO
Wood Frame 1/16/2025 Approved RONNIE MINDANAO
Special/Order Compliance 1/14/2026 No Access for Inspection ALEX COLIN