2041 S PALM GROVE AVE 90016

Certificate Information: 2041 S PALM GROVE AVE 90016

Application / Permit
21016-20000-58799
Plan Check / Job No.
B21VN17736
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO CREATE A NEW BEDROOM AND BATHROOM AND ADD A NEW BEAM AND HEADER, PER ENG. "COMPLY WITH DEPARTMENT ORDER effective date 09/14/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
Permit Finaled on 11/18/2022

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 OMAR GARNICA
Corrections Issued 12/22/2021 OMAR GARNICA
Plan Check Approved 1/18/2022 OMAR GARNICA
Building Plans Picked Up 1/20/2022 APPLICANT
Issued 1/28/2022 APPLICANT
Permit Finaled 11/16/2022 WILLIAM MICHALAK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/28/2021 ERIK BEASLEY
Sewer availability Cleared 12/28/2021 ERIK BEASLEY

Contact Information

Contractor Ahn'S Construction; Lic. No.: 1022756-B 13330 BLOOMFIELD AVENUE   SUITE 220    NORWALK, CA 90650
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/22/2022 Not Ready for Inspection WILLIAM MICHALAK
HVAC-Rough 2/22/2022 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 2/22/2022 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 4/29/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 5/24/2022 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 5/24/2022 Partial Approval WILLIAM MICHALAK
Wood Frame 5/24/2022 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 10/25/2022 No Access for Inspection WILLIAM MICHALAK
Final 10/25/2022 No Access for Inspection WILLIAM MICHALAK
MERV13>=Final 10/25/2022 No Access for Inspection WILLIAM MICHALAK
MERV13>=Rough 10/25/2022 No Access for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 10/25/2022 No Access for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 10/26/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Final 10/26/2022 Partial Approval WILLIAM MICHALAK
Final 10/26/2022 Corrections Issued WILLIAM MICHALAK
Gas Test 10/26/2022 Corrections Issued WILLIAM MICHALAK
HVAC-Final 10/26/2022 Corrections Issued WILLIAM MICHALAK
MERV13>=Final 10/26/2022 Approved WILLIAM MICHALAK
MERV13>=Rough 10/26/2022 Approved WILLIAM MICHALAK
PLUMBING-Final 10/26/2022 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 10/26/2022 Approved WILLIAM MICHALAK
Final 11/10/2022 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved WILLIAM MICHALAK
Final 11/16/2022 Permit Finaled WILLIAM MICHALAK