17431-17435 W DEVONSHIRE ST 91325
Certificate Information: 17431-17435 W DEVONSHIRE ST 91325
- Application / Permit
- 21016-20000-58682
- Plan Check / Job No.
- B21VN17642
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 10' X 17'-10" PORTION OF SFD TO STORAGE ROOM. CONVERT 15'-8" X 20'-5" IRREG SHAPED PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. CONVERT 15'-6" X 20'-5" IRREG SHAPED PORTION OF SFD TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 12/31/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 1/20/2022 | AUNG SOE |
| Plan Check Approved | 1/24/2022 | AUNG SOE |
| Building Plans Picked Up | 2/8/2022 | APPLICANT |
| Issued | 2/28/2022 | APPLICANT |
| CofO in Progress | 1/26/2023 | DAVID SCANTLIN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/10/2022 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Address approval | Cleared | 1/11/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 6/7/2022 | Partial Approval | JEFFREY PARD |
| Underground Mechanical | 6/7/2022 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 6/23/2022 | Approved | JEFFREY PARD |
| Insulation | 7/1/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 7/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 7/21/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | KRISTEN CAUSEY |
| Deputy Wood Construction | 7/26/2022 | Conditional Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 7/26/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 7/26/2022 | Approved | JEFFREY PARD |
| Insulation | 8/1/2022 | Corrections Issued | JESUS PINEDA |
| Insulation | 8/4/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 8/15/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/6/2022 | Approved | JEFFREY PARD |
| Final | 9/6/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 9/6/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 9/6/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 9/6/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 11/30/2022 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 11/30/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 1/25/2023 | Approved | DAVID SCANTLIN |
| Final | 1/25/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 1/25/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 1/25/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 1/25/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Approved | DAVID SCANTLIN |