24800-24802 W EILAT ST 91367
Certificate Information: 24800-24802 W EILAT ST 91367
- Application / Permit
- 21016-20000-58663
- Plan Check / Job No.
- B21VN17629
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/17/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/10/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Plan Check Approved | 8/23/2023 | ROSENDO MEDINA |
| Issued | 8/23/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | TROY SANDERS |
| CofO Issued | 3/22/2024 | JOHN JANSON |
| Permit Finaled | 3/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 8/18/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | COLIN LOREDO |
| Tract Map conditions | Cleared | 8/21/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 8/21/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 8/21/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jafari,, Masoud; Lic. No.: S3812 | 23 ORCHARD SUITE 250 LAKE FOREST, CA 92630 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2023 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 10/5/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/23/2023 | Approved | TROY SANDERS |
| Green Building Rough | 10/23/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/23/2023 | Approved | TROY SANDERS |
| Insulation | 11/13/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 11/13/2023 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 11/16/2023 | Approved | TROY SANDERS |
| Final | 1/5/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 1/5/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 1/5/2024 | Approved | TROY SANDERS |