12502 W RYE ST 91604
Certificate Information: 12502 W RYE ST 91604
- Application / Permit
- 21016-20000-58600
- Plan Check / Job No.
- B21VN17606
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-1" X 28' ADDITION TO (E) SFD.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/31/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/1/2022 | SERGIO MUNIZ |
| Plan Check Approved | 3/16/2022 | SERGIO MUNIZ |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 10/3/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/4/2022 | MICHAEL SMITH |
| CofO Issued | 10/4/2022 | MICHAEL SMITH |
| Permit Finaled | 10/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 2/16/2022 | LAUREN PADICK |
| ZA Case | Cleared | 2/16/2022 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2022 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/22/2022 | No Access for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 3/25/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 3/29/2022 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 3/29/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/8/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/8/2022 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/8/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/8/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/13/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/13/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/13/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/13/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 4/14/2022 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | CALEB MEISTER |
| Insulation | 4/25/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 4/29/2022 | Approved | CALEB MEISTER |
| Shower Pan | 4/29/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 5/4/2022 | No Access for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/9/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/6/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/6/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 7/12/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/12/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Green Building Final | 7/12/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 7/12/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 7/12/2022 | Approved | CHRISTOPHE COCHRAN |