4546 N KATHERINE AVE 91423
Certificate Information: 4546 N KATHERINE AVE 91423
- Application / Permit
- 21016-20000-58504
- Plan Check / Job No.
- B21VN17549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17' 8" X 20' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/24/2022
- Issuing Office
- Current Status
- CofO Issued on 9/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/24/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/28/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/7/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| Issued | 4/24/2022 | APPLICANT |
| CofO in Progress | 9/14/2022 | MISAEL ESPARZA |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
| CofO Issued | 9/15/2022 | MICHAEL SMITH |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/6/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 1/6/2022 | LAUREN PADICK |
Contact Information
| Contractor | Livewell Remodeling & Construction; Lic. No.: 1049024-B | 4365 MAMMOTH AVE APT 205 SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/4/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/6/2022 | Approved | MISAEL ESPARZA |
| Sewer | 5/11/2022 | Approved | MISAEL ESPARZA |
| Gas Test | 5/16/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/2/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/2/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 6/2/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 6/2/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 6/2/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/8/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/8/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 6/8/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 6/14/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 6/21/2022 | Approved | CALEB MEISTER |
| Insulation | 6/21/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/21/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/22/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/29/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/12/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/12/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/12/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/12/2022 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Final | 8/12/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/12/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 8/12/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/17/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/17/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/17/2022 | Approved | MISAEL ESPARZA |
| Final | 9/13/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 9/13/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | MISAEL ESPARZA |