4291 1/4 N TUJUNGA AVE 91604
Certificate Information: 4291 1/4 N TUJUNGA AVE 91604
- Application / Permit
- 21016-20000-58499
- Plan Check / Job No.
- B21VN17541
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-3" X 33'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ATTACHED LAUNDRY ROOM TO REMAIN. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/26/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 3/27/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 1/9/2023 | ROBERT DAVIS |
| CofO Issued | 1/24/2023 | RICKEY JACKSON |
| Permit Finaled | 1/24/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/4/2022 | AMIR KASHFI |
| "Q" conditions | Cleared | 1/5/2022 | LAUREN PADICK |
| "T" removal | Cleared | 1/5/2022 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | AMIR KASHFI |
| Tenant Habitability Plan | Cleared | 1/5/2022 | RICHARD BRINSON |
| ZI | Cleared | 1/5/2022 | LAUREN PADICK |
| Construction near power lines | Cleared | 3/14/2022 | TINA MIRANDA |
Contact Information
| Contractor | La Top Builders Inc; Lic. No.: 1077576-B | 20701 EXHIBIT PL WOODLAND HILLS, CA 91367 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2022 | Approved | BRUCE CAMPBELL |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 6/13/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 7/6/2022 | Approved | ROBERT DAVIS |
| Wood Frame | 7/6/2022 | Approved | ROBERT DAVIS |
| Insulation | 7/18/2022 | Approved | ROBERT DAVIS |
| Drywall Nailing | 7/25/2022 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 7/27/2022 | Approved | ROBERT DAVIS |
| Final | 10/14/2022 | Corrections Issued | ROBERT DAVIS |
| Green Building Final | 10/14/2022 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 10/14/2022 | Approved | ROBERT DAVIS |
| Final | 11/30/2022 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 11/30/2022 | Approved | ROBERT DAVIS |
| Smoke Detectors | 11/30/2022 | Approved | ROBERT DAVIS |