162 1/4 W 89TH ST 90003
Certificate Information: 162 1/4 W 89TH ST 90003
- Application / Permit
- 21016-20000-58473
- Plan Check / Job No.
- B21VN17516
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 16'-0" X 36'-4" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/25/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/4/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/13/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Plan Check Approved | 7/25/2022 | LUISANGEL VALENZUELA |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 9/11/2024 | MICHAEL LEWIS |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2021 | JEANIE LAM |
| Sewer availability | Cleared | 12/30/2021 | JEANIE LAM |
Contact Information
| No Data Available. |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/26/2023 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/31/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/31/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 1/9/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/9/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/21/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/21/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 2/21/2024 | Approved | MICHAEL LEWIS |
| Wood Frame | 2/21/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/7/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/7/2024 | Approved | MICHAEL LEWIS |
| Insulation | 3/7/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 3/15/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 3/15/2024 | Approved | MICHAEL LEWIS |
| Insulation | 4/25/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 4/30/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 6/24/2024 | Approved | AMY COLIN |
| ELECTRICAL-Final | 6/25/2024 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 6/25/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/28/2024 | Approved | JOSH MEISTER |
| Sewer | 7/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 7/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 7/18/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 7/18/2024 | Partial Approval | JOSH MEISTER |
| Underground Mechanical | 8/21/2024 | Approved | MICHAEL LEWIS |
| Final | 8/30/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 8/30/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 8/30/2024 | Approved | CRAIG DAVIS |
| Final | 9/10/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 9/10/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Approved | MICHAEL LEWIS |