162 1/4 W 89TH ST 90003

Certificate Information: 162 1/4 W 89TH ST 90003

Application / Permit
21016-20000-58473
Plan Check / Job No.
B21VN17516
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 16'-0" X 36'-4" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 7/25/2022
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 RAPHAEL ROSAS
Corrections Issued 12/25/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/4/2022 RAPHAEL ROSAS
Applicant returned to address corrections 7/13/2022 RAPHAEL ROSAS
Building Plans Picked Up 7/18/2022 APPLICANT
Plan Check Approved 7/25/2022 LUISANGEL VALENZUELA
Issued 7/25/2022 APPLICANT
CofO in Progress 9/11/2024 MICHAEL LEWIS
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/30/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/30/2021 JEANIE LAM
Sewer availability Cleared 12/30/2021 JEANIE LAM

Contact Information

No Data Available.

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/26/2023 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/31/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/31/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 1/9/2024 Approved MICHAEL LEWIS
Underground Mechanical 1/9/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 2/21/2024 Approved MICHAEL LEWIS
HVAC-Rough 2/21/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 2/21/2024 Approved MICHAEL LEWIS
Wood Frame 2/21/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/7/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Approved MICHAEL LEWIS
HVAC-Rough 3/7/2024 Approved MICHAEL LEWIS
Insulation 3/7/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 3/15/2024 Approved MICHAEL LEWIS
Green Building Rough 3/15/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 3/15/2024 Approved MICHAEL LEWIS
Insulation 4/25/2024 Approved MICHAEL LEWIS
Drywall Nailing 4/30/2024 Approved MICHAEL LEWIS
Shower Pan 6/24/2024 Approved AMY COLIN
ELECTRICAL-Final 6/25/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 6/25/2024 Not Ready for Inspection MICHAEL LEWIS
Interior/Exterior Lathing 6/28/2024 Approved JOSH MEISTER
Sewer 7/16/2024 Corrections Issued MICHAEL LEWIS
Underground Mechanical 7/16/2024 Corrections Issued MICHAEL LEWIS
Sewer 7/18/2024 Approved JOSH MEISTER
Underground Mechanical 7/18/2024 Partial Approval JOSH MEISTER
Underground Mechanical 8/21/2024 Approved MICHAEL LEWIS
Final 8/30/2024 Corrections Issued CRAIG DAVIS
Green Building Final 8/30/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 8/30/2024 Approved CRAIG DAVIS
Final 9/10/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 9/10/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved MICHAEL LEWIS